Project Overview
This project was a continuation of the work originally undertaken by Other well know company (Bajaj Electricals Limited).
We are also pleased to share that the client, MPPTCL, has expressed their appreciation for the successful and efficient completion of the work.
YEAR
2019
Project Challenges
Despite facing several challenges, including tough site conditions, right-of-way (ROW) issues, and stringing work in hilly terrain, we successfully completed and commissioned the line within 10 months after the site was handed over to us. Our team’s commitment and perseverance ensured the timely delivery of the project.