Project Overview
Following the handover of the land to Vikran, we successfully completed and commissioned the substation in a record time of just 14 months. Below are the key details of the work completed:
- 2 Nos. 50 MVA Power Transformers
- 2 Nos. 132/33 kV Transformer Bays
- 2 Nos. 132 kV Feeder Bays
- 1 No. 132 kV Bus Coupler Bay
- 2 Nos. 33 kV Transformer Bays
- 2 Nos. 33 kV Feeder Bays
- 1 No. 33 kV Capacitor Bank
For this achievement, we received appreciation from the client for our timely and quality execution of the project.
YEAR
2019
![](https://www.vikrangroup.com/storage/uploads/yCiOy7gYW2otdWLiXdxkkX4gVbNyHeFuU10ADLJA.jpg)
Project Challenges
Despite facing several challenges, including tough site conditions, right-of-way (ROW) issues, and stringing work in hilly terrain, we successfully completed and commissioned the line within 10 months after the site was handed over to us. Our team’s commitment and perseverance ensured the timely delivery of the project.